top of page

Vantage Data Center

About the Project

Address

2133 M St NE

Quincy, WA 98848

Owner:

Vantage Data Centers LLC

General Contractor:

Foushee & Associates, Co., Inc.

Architect:

Corgan

Structural Engineer:

Paradigm Structural Engineers

Project Metrics

Concrete Poured:

6,900 cy

Horizontal Finished:

195,403 sf

Vertical Formed:

52,000 sfca

Rebar Placed

3,400 tons

Cables Placed

-